In MacProject II, you specify the dependencies by connecting the task and milestone boxes in the Schedule Chart.
(This is the only chart to show
dependencies.)
A line appears between two boxes that have been connected, so that you can readily see the sequence of dependent tasks.
-- part contents for background part 7
----- text -----
Because a dependent task always occurs after the task on which it depends, you can draw dependency lines only from left to right. You cannot move a dependent task to the left of the task on which it depends.
You can add lag time to a dependency between two tasks.